Audit
ITEMS APPEARING TO BE IN SAFE WORKING ORDER SHALL BE MARKED "YES" ITEMS IDENTIFIED AS DEFECTIVE OR UNSAFE SHALL BE MARKED "NO" AND MUST BE REPORTED TO THE FLEET MANAGER IMMEDIATELY
CHOOSE TYPE OF PLANT TO BE INSPECTED:
CHECK ITEMS:
INFORMATION:
Items of Plant Requiring Workcover Registration
• Amusement structures.
• Boilers and pressure equipment
• Building maintenance units
• Concrete placing units (truck mounted with boom)
• Lifts
• Mobile cranes
• Tower cranes
Loadshifting Plant Requiring Notice of Assessment
LF - Forklift Trucks
LO - Order-picking Forklift Trucks
LC - Cableway/Flying Foxes
LB - Front-end Loader/Backhoes
LL - Front End Loader
LS - Front End Loader (Skid Steer Types)
LE - Excavators
LD - Draglines
LZ - Dozers
These codes often appear on the Operator’s Certificate of Competency or Notice of Assessment without stating the type of plant which they represent
Categories of Plant Requiring a Certificate of Competency
Certificates of Competency are no longer issued for Loadshifting equipment. The registered assessor will issue a Notice Of Assessment, which must be kept by the operator as proof of competency. Certificates of competency are recognised in all States & Territories
Scaffolding
SB - Basic scaffolding
SI - Intermediate scaffolding
SA - Advanced Scaffolding
Rigging
DG - Dogging
RB - Basic rigging
RI - Intermediate rigging
RA - Advanced rigging
Pressure equipment
BB - Basic boiler
BI - Intermediate boiler
BA - Advanced boiler
TO - Turbine operator
ES - Reciprocating steam engine
PB - Concrete placing boom
Crane & hoist operation
CT - Tower crane
CD - Derrick crane
CP - Portal boom crane
CB - Bridge or gantry crane
CV - Vehicle loading crane
CN - Non-slewing mobile crane (over 3 tonnes)
C2 - Slewing mobile crane (up to 20 tonnes)
C6 - Slewing mobile crane (up to 60 tonnes)
C1 - Slewing mobile crane (up to 100 tonnes)
C0 - Slewing mobile crane (over 100 tonnes)
WP - Boom-type elevating work platform (boom length 11 metres or more)
HM - Materials hoist (cantilever platform)
HP - Personnel (and materials) hoist
Except in an emergency or under a Worksafe / Workcover exemption, a person must not perform or direct another person to perform the work using any of the above items of plant unless the person doing the work has the appropriate certificate of competency. The maximum number of persons without a certificate being supervised by a person who holds the relevant certificate is limited as follows
Supervisor holds certificate for work listed in:
Schedule A of the National Standard (ie scaffolding & rigging) Maximum number of persons without certificate being supervised: 4
Schedule B or C of the National Standard (all other categories) Maximum number of persons without certificate being supervised: 1